Here’s a look at work planned in the district for the week starting June 20, 2022. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues. Motorists are advised to remain alert and pay special attention to all signs, barricades and traffic controls, and reduce their speed as they approach and travel through work zones. They should also avoid distractions such as cell phones, eating, drinking, or car audio or navigation systems.

Greenville Area (Hunt, Rains Counties)

Sidewalk and Curb Ramp Project (several counties): The contractor has set barricades at the Pottsboro, Texas location. The contractor is currently working on FM 120 between Festival Street and Ginger Drive. The work will require removing existing concrete and pouring proposed sidewalk and driveways. This project will improve pedestrian sidewalks and construct ADA-compliant curb ramps at these locations. Please be aware of workers and watch for work zones when traveling in this area.

FM 903, Hunt County: From US 380 to FM 1569 South. The contractor’s work this week consisted of watering the base, and ditch work. Next, the contractor plans to resume cement treat operations scheduled for June 21-24. A ride quality test and prime coat will follow, and then work will move on to mile three.

FM 275, Rains County: from SH 19 to FM 514. The contractor has completed widening and reworking existing base for the last section of the project. The contractor will continue setting safety end treatments and driveway pipe on the south side of the project once material delays are resolved. Finishing base and preparing for prime coat should be back on schedule by June 20. Please be aware of lane closures, detours, and watch for work zones and workers when traveling in this area.

SH 276, Hunt County: from FM 36 to SH 34 (Quinlan Bypass). The contractor completed the concrete paving on the intersection of SH 276 and FM 264. The contractor is working on the culvert extension on the west section SH 276. The contractor is working on ditch and back slope grading – preparing areas for scheduled temporary seeding, and addressing side walks and ADA ramp installation. Please be aware of lane closures and watch for work zones and workers when traveling in this area.

FM 1566, Hunt County: from FM 272 near Celeste to State Highway 34. The contractor has finished mailbox turnouts. The contractor is working on the proposed signs for the project. The contractor completed the first course for the road surface this week. The second course will be scheduled later next week. Please be aware of lane closures, detours, and watch for work zones and workers when traveling in this area.

Maintenance crews for both Hunt and Rains County will be performing seal coat operations on FM 499 from SH 24 to the county line, and FM 118 from SH 224 to FM 512. The contractor will be performing full depth concrete repair in spots on I-30 and on Monte Stratton Boulevard, from 6 pm to 6 am Crews will be performing potholing at various locations in Hunt County. Hunt County maintenance crews placed changeable message boards on both SH 66 and FM 1570 to warn drivers of pending intersection changes (four-way stop). Maintenance crews will be installing mailboxes, delineators, and signs in various locations. Please be careful when traveling in these areas, watch out for workers and maintain a safe distance from work crews.